4.1.2 Application—The sequential activities described
herein are intended to produce an evaluation program, but all
activities may not be applicable or necessary for a particular
evaluation program. It is the responsibility of the professional
using this guide to determine the activities and sequence
necessary to perform an appropriate leakage evaluation for a
specific low-sloped roof on a building.
4.1.3 Preliminary Assessment—A preliminary assessment
may indicate that water leakage problems are limited to a
specific element or portion of a low-sloped roof. The evalua-
tion of causes may be limited in scope, and the procedures
recommended herein abridged according to the professional
judgment of the investigator. A statement stipulating the limits
of the investigation should be included in the report.
4.1.4 Expectations—Expectations about the overall effec-
tiveness of an evaluation program must be reasonable, and in
proportion to a defined scope of work. This guide is intended
to address leakage of a low-sloped roof system, leading to
conclusions that can generally be applied to similar or other
locations on the roof. Since every possible location is not
included in an evaluation program, it is probable that every
leak source will not be identified. Leak sources that are
localized and unique may remain, and require specific and
localized evaluation effort.
4.2 This guide is not intended as a design guide. Reference
is made to design features of a low-sloped roof only for the
purpose of identifying items of interest for consideration in the
evaluation process.
4.3 This guide does not address leakage through walls not
associated with roof construction, fenestration, or leakage
below-grade. It is not intended for use with structures designed
to retain water, such as pools, fountains, and vegetative roofs.
SYSTEMATIC APPROACH TO AN EVALUATION
5. Overview
5.1 The methodology presented in this guide is intended to
provide a systematic approach to evaluating roof leaks, and is
applicable to any low-sloped roof system. The sequence of
activities is intended to lead to an accumulation of information
in an orderly and efficient manner, so that each step enhances
and supplements the information gathered in the preceding
step.
5.1.1 Sequence of Activities—The recommended sequence
of activities, discussed in individual sections below are:
5.1.1.1 Review of project documents.
5.1.1.2 Evaluation of original roof design concept.
5.1.1.3 Determination and review of service history.
5.1.1.4 Inspection.
5.1.1.5 Investigative testing.
5.1.1.6 Analysis.
5.1.1.7 Report preparation.
5.2 Analysis and Interpretation—The information gathered
during a leakage evaluation is analyzed as it is acquired. It is
not the intent of this guide to imply that the analysis and
interpretation of the information occurs only at the completion
of all activities.
6. Review of Project Documents
6.1 Ideally, project documents, including roof component
shop drawings, will be available and accessible for review. The
discussion in this section assumes that a project was organized
on a conventional owner/design professional/contractor model.
Projects can be delivered in various ways, and the method used
will dictate the appropriate organization of the project docu-
ments. The information discussed below should be available
for review somewhere in the project documents.
6.1.1 Design, Bidding, and Contract Documents—These
documents include architectural and engineering drawings,
specifications, and may include correspondence, meeting
minutes, addenda, substitution proposals, product literature,
test reports, survey reports prepared by others, shop drawings,
and so forth. They contain the information necessary to
understand the performance criteria, the design intent,
materials, and relationships among the roof components.
6.1.1.1 Documents may be revised or supplemented over
the course of construction. Revisions to drawings are typically
recorded by number and date, with a cross reference to other
accompanying documents. Reviewing all revisions and under-
standing the differences between them and the reason for the
differences is part of the evaluation.
6.1.1.2 Documents with the most recent issue date and the
highest revision number establish the requirements for the
project. A set of documents marked “as-built” or “record set”
are intended to show the actual construction and may be
available.
6.2 Referenced Codes and Standards—Project documents
usually contain references to regulatory codes, industry
standards, or manufacturer installation requirements.
Standards, referenced codes, and manufacturer information
often contain default or minimum criteria to establish the
performance criteria for the roof. Conflicts between the refer-
enced documents and those stated in the project documents
should not be assumed to be a cause of leakage without further
investigation.
6.2.1 Regulatory codes, industry standards, and manufac-
turer installation requirements change over time. The version
of these documents examined as part of the review of project
documents should be those listed with dates in the project
documents, or if not listed with dates, those in effect when the
building permit was issued.
6.3 Submittals—Additional documents are generated after
the award of contracts and are submitted to the design
professional for review and inclusion in the project record. The
submittals usually apply to a specific material, component,
assembly, or installation method, and the information con-
tained will augment the project documents. There can be a
number of revisions to submittals prior to final approval. The
standard for the project is set by the submittals approved by the
design professional. Submittals can include shop drawings, test
reports, product literature, manufacturers’ recommendations,
installation and maintenance guidelines, warranties, etc.
6.3.1 Test reports provided by manufacturers and suppliers
should have been performed by an independent laboratory or
witnessed by an independent agency (if requested by the