6. Sampling
6.1 Obtain the sample of freshly mixed concrete in accor-
dance with Practice C172/C172M in the field, or Practice
C192/C192M in the laboratory, and place it in the sample
receptacle. If the nominal maximum size of coarse aggregate
exceeds 1
1
⁄
2
-in. [37.5 -mm], wet-sieve a sufficient amount of
the representative sample over a 37.5-mm (1
1
⁄
2
-in.) sieve in
accordance with Practice C172/C172M to yield enough mate-
rial to fill the cone.
NOTE 6—Information regarding the nominal maximum size of the
coarse aggregate should be available from the concrete mixture propor-
tions.
7. Procedure
7.1 Dampen the mold and place it on a rigid, flat, level,
moist, nonabsorbent surface, free of vibration, and that is large
enough to contain all of the slumped concrete. It shall be held
firmly in place during filling and perimeter cleaning by the
operator standing on the two foot pieces or by a clamping
arrangement to a base plate as described in 5.1. From the
sample of concrete obtained in accordance with Section 6,
immediately fill the mold in three layers, each approximately
one third the volume of the mold (See Note 7). Place the
concrete in the mold using the scoop described in 5.4. Move
the scoop around the perimeter of the mold opening to ensure
an even distribution of the concrete with minimal segregation.
NOTE 7—One third of the volume of the slump mold fills it to a depth
of 2
5
⁄
8
in. [70 mm]; two thirds of the volume fills it to a depth of 6
1
⁄
8
in.
[160 mm].
7.2 Rod each layer 25 times uniformly over the cross
section with the rounded end of the rod. For the bottom layer,
this will necessitate inclining the rod slightly and making
approximately half of the strokes near the perimeter, and then
progressing with vertical strokes spirally toward the center.
Rod the bottom layer throughout its depth. For each upper
layer, allow the rod to penetrate through the layer being rodded
and into the layer below approximately 1 in. [25 mm].
7.3 In filling and rodding the top layer, heap the concrete
above the mold before rodding is started. If the rodding
operation results in subsidence of the concrete below the top
edge of the mold, add additional concrete to keep an excess of
concrete above the top of the mold at all times. After the top
layer has been rodded, strike off the surface of the concrete by
means of a screeding and rolling motion of the tamping rod.
Continue to hold the mold down firmly and remove concrete
from the area surrounding the base of the mold to preclude
interference with the movement of slumping concrete. Remove
the mold immediately from the concrete by raising it carefully
in a vertical direction. Raise the mold a distance of 12 in. [300
mm] in 5 62 s by a steady upward lift with no lateral or
torsional motion. Complete the entire test from the start of the
filling through removal of the mold without interruption and
complete it within an elapsed time of 2
1
⁄
2
min.
7.4 Immediately measure the slump by determining the
vertical difference between the top of the mold and the
displaced original center of the top surface of the specimen. If
a decided falling away or shearing off of concrete from one
side or portion of the mass occurs (Note 8), disregard the test
and make a new test on another portion of the sample.
NOTE 8—If two consecutive tests on a sample of concrete show a falling
away or shearing off of a portion of the concrete from the mass of the
specimen, the concrete probably lacks necessary plasticity and cohesive-
ness for the slump test to be applicable.
8. Report
8.1 Report the slump in terms of inches [millimetres] to the
nearest
1
⁄
4
in. [5 mm] of subsidence of the specimen during the
test.
9. Precision and Bias
4
9.1 Precision—The estimates of precision for this test
method are based upon results from tests conducted in
Fayetteville, Arkansas by 15 technicians from 14 laboratories
representing 3 states. All tests at 3 different slump ranges, from
1.0 in. [25 mm] to 6.5 in. [160 mm], were performed using one
load of truck-mixed concrete. The concrete was delivered and
tested at a low slump, with water then being added and mixed
into the remaining concrete to independently produce moderate
and finally high-slump concrete. The concrete mixture that
used a No. 67 crushed limestone aggregate and a washed river
sand, contained 500 lb of cementitious materials per cubic yard
[297 kg of cementitious material per cubic metre]. The 500 lb
[227 kg] were equally divided between a C150, Type I/II
cement and a Class C fly ash. A double dosage of a chemical
retarder was used in an attempt to minimize slump losses and
maintain workability of the concrete. Concrete temperatures
ranged from 86 °F to 93 °F [30 °C to 34 °C]. Slump losses
averaged 0.68 in. [17 mm] during the 20 min required to
perform a series of 6 tests at 1 slump range. Testing was
performed alternately using metal and plastic molds, which
were determined to produce comparable results. Precision data
thus applies to both metal and plastic molds. A total of 270
slump tests were performed.
9.1.1 Inch-Pound [SI]—The data used to develop the preci-
sion statement were obtained using metric units (millimetres).
The precision values shown in inch-pound units are conver-
sions from the millimetre measurements, which were recorded
to the nearest 1 mm.
9.1.2 Measure of Variability—The standard deviation was
determined to be the most consistent measure of variability and
was found to vary with the slump value.
9.1.3 Single-Operator Precision—The single-operator stan-
dard deviation represented by (1s) is shown in Table 1 by
average slump values. The reported results for the replicate
readings apply to tests conducted by the same operator
performing successive tests, one immediately following the
other. Acceptable results of two properly conducted tests by the
same operator on the same material (Note 9) will not differ
from each other by more than the (d2s) value of the last column
of Table 1 for the appropriate slump value and single-operator
precision.
4
The test data used to develop this precision statement were based on tests
performed in September 1997. Supporting data have been filed at ASTM Interna-
tional Headquarters and may be obtained by requesting Research Report RR:C09-
1022. Contact ASTM Customer Service at www.astm.org/contact.
C143/C143M − 26